File #: 09-0190    Version: 1
Type: Agenda Item Status: Approved
File created: 2/4/2009 In control: Board of Supervisors
On agenda: 4/21/2009 Final action: 4/21/2009
Title: Transportation Department recommending the Board authorize the Chairman to sign the Utility Agreement AGMT 08-52583 and Joint Use Agreement No. 2462.3L with AT&T California in a not to exceed amount of $140,084.96 for the relocation of existing telephone facilities for the US Highway 50 /Missouri Flat Road Interchange Improvements - Phase 1B Project 71336. FUNDING: Missouri Flat Master Circulation and Funding Plan (MC&FP).
Attachments: 1. Utility Agreement.PDF, 2. County Counsel Utility Agmt.PDF, 3. Joint Use Agreement.PDF, 4. County Counsel Joint Use.PDF
Title
Transportation Department recommending the Board authorize the Chairman to sign the Utility Agreement AGMT 08-52583 and Joint Use Agreement No. 2462.3L with AT&T California in a not to exceed amount of $140,084.96 for the relocation of existing telephone facilities for the US Highway 50 /Missouri Flat Road Interchange Improvements - Phase 1B Project 71336.

FUNDING: Missouri Flat Master Circulation and Funding Plan (MC&FP).

Body
BUDGET SUMMARY:
Total Estimated Cost $140,084.96

Funding
Budgeted* $140,084.96
New Funding $
Savings $
Other $
Total Funding Available $140,084.96
Change To Net County Cost $0.00
* included in the proposed FY 09/10 project budget.

Fiscal Impact/Change to Net County Cost:
Funding for Utility and Joint Use Agreements (the Agreements) are provided by the MC&FP and has been included in the proposed work program budget for FY 09/10, identified as project number 71336. The County's total expense associated with the Agreements is estimated to be $112,067.97. The Agreements are an actual cost contract for the described work and language in the Agreements allows for the expenditure of 125% of this amount or an additional $28,016.99, before the Agreements require amending. Therefore, the Agreements not to exceed amount is $140,084.96. There is no net cost to the County General Fund associated with this agenda item.

Reason for Recommendation:
The Agreements will assist the Department in meeting its goal of delivering the U.S. Highway 50/Missouri Flat Road Interchange Improvements - Phase 1B Project #71336 (Project). The Agreements define the roles and obligations of both El Dorado County and AT&T for the relocation of the utility facilities to accommodate the construction of the Project. A previous Agreement was processed for the AT&T relocation of facilities for construction of Phase 1A.

The County as the lead agency on the Project is responsible for the des...