File #: 20-1397    Version: 1
Type: Agenda Item Status: Approved
File created: 10/13/2020 In control: Board of Supervisors
On agenda: 11/10/2020 Final action: 11/10/2020
Title: Department of Transportation recommending the Board: 1) Approve and authorize the Chair to sign the Notice of Acceptance with Robert A. Bothman Construction for the Greenstone Road at Slate Creek Bridge Replacement Project, CIP 77137/36105019, Contract 3605; and 2) Approve and authorize the Clerk of the Board to release the Payment and Performance Bonds to the Surety upon notification from the Department of Transportation, after the one-year guarantee period. FUNDING: Highway Bridge Program (99%), RSTP Exchange Funds (<1%), Road Fund (<1%). (Federal Funds).
Attachments: 1. A - Notice of Acceptance, 2. Executed NOA Contract 3605

Title

Department of Transportation recommending the Board:

1) Approve and authorize the Chair to sign the Notice of Acceptance with Robert A. Bothman Construction for the Greenstone Road at Slate Creek Bridge Replacement Project, CIP 77137/36105019, Contract 3605; and

2) Approve and authorize the Clerk of the Board to release the Payment and Performance Bonds to the Surety upon notification from the Department of Transportation, after the one-year guarantee period.

 

FUNDING: Highway Bridge Program (99%), RSTP Exchange Funds (<1%), Road Fund (<1%). (Federal Funds).

Body

DISCUSSION / BACKGROUND

The contract for the Project was approved by the Board on May 14, 2019 (Item 24) and the roadway was opened to the public on October 1, 2020.  Recordation of the Notice of Acceptance (NOA) will start legal time frames for guarantees, a lien period, and return of retention monies.  Recordation of the NOA will also start the one-year time frame for releasing the Payment and Performance Bonds to the Surety.

 

Direct Construction Cost Summary:

 

Original Bid Price                     $ 2,125,000

Contract Item Cost                     $ 2,131,212

Contract Change Order Cost                     $      59,850

Total Direct Construction Cost                     $ 2,191,062

Direct Construction Budget                     $ 2,339,100

 

Major contract change orders included constructing additional drainage to address surface drainage run-on at the northeast section of the project and modifications to the alternative terminal end systems.

 

The final costs listed are estimates.  Transportation will be closing out the Project with the Contractor and finalizing costs over the coming weeks.  Any significant deviations from the estimates above that exceed Transportation’s allocated authority will be brought back to the Board for review and approval in a subsequent agenda item.

 

ALTERNATIVES

The Board could choose not to approve the NOA.  Transportation staff would make modifications as directed by the Board and return for Board approval of the NOA.  This would delay the release of the Payment and Performance Bonds and extend the Contractor’s warranty period.

 

PRIOR BOARD ACTION

See Discussion / Background section above.

 

OTHER DEPARTMENT / AGENCY INVOLVEMENT

N/A

 

CAO RECOMMENDATION

Approve as recommended.

 

FINANCIAL IMPACT

There is no change to Net County Cost associated with this item.  The Project is budgeted in Transportation’s 2020 CIP, which was approved by the Board on June 09, 2020 (Item 54).  The anticipated direct construction cost is less than the direct construction budget established by the Board.

 

CLERK OF THE BOARD FOLLOW UP ACTIONS

1) The Clerk of the Board will obtain the Chair’s signature on one (1) original of the NOA.

2) The Clerk of the Board will send the fully executed original of the NOA to the Recorder/Clerk’s Office for recordation within ten (10) days, and forward a copy of the recorded NOA to Transportation, Headington Engineering, Attention: John Kahling.

3) One (1) year after the recordation of the NOA, Transportation will verify that all warranty work, if any, has been satisfactorily completed and will notify the Clerk of the Board in writing to release the Payment and Performance Bonds.

 

STRATEGIC PLAN COMPONENT

Infrastructure

 

CONTACT

Rafael Martinez, Director

Department of Transportation