Title
Department of Transportation recommending the Board adopt a resolution to claim an allocation of $140,000 of Transportation Development Act, Article 3 funds for the Northside School Bike Path Phase 2, project 72306.
FUNDING: Transportation Development Act (TDA) Article 3 Funds.
Resolution 060-2011
Body
BUDGET SUMMARY: |
|
|
Total Estimated Cost |
|
$ 140,000 |
|
|
|
Funding |
|
|
Budgeted |
$ 38,000 |
|
New Funding |
$ |
|
Savings |
$ |
|
Other |
$ 102,000 |
|
Total Funding Available |
$ |
|
Change To Net County Cost |
|
$ |
To be included in the department's 11/12 budget.
Fiscal Impact/Change to Net County Cost: These funds will provide the matching funds to the Safe Routes to School grant.
Background: On October 1, 2009, the El Dorado County Transportation Commission (EDCTC) adopted Resolution 09/10.06 allocating $140,000 in Transportation Development Act (TDA) Funds to El Dorado County Department of Transportation, to be used for Article 3 purposes. Article 3 of the TDA permits counties to file claims for bicycle and pedestrian projects.
Reason for Recommendation: The TDA Article 3 funds will provide additional funding for the Northside School Bike Path project. The Northside School Class I Bike Path - Phase 2 (SR49) project is included in the adopted 2010 Capital Improvement Program (CIP) as project 72306.
Action to be taken following Board approval: Upon approval of the recommendation, DOT will file a claim signed by the Director of Transportation for TDA Article 3 funds with the EDCTC, with said funds to be used on the Northside School Bike Path, project 72306.
Contact: James W. Ware, P.E.