File #: 25-0700    Version: 1
Type: Agenda Item Status: Consent Calendar
File created: 4/8/2025 In control: Board of Supervisors
On agenda: 5/13/2025 Final action:
Title: Facilities, a division of the Chief Administrative Office, recommending the Board consider the following pertaining to the annual Job Order Contracting Bid that allows the County to efficiently bid multiple construction jobs throughout the year based on competitively bid unit prices: 1) Approve and adopt the bid, specifications, and contract documents; 2) Approve and authorize the Chair to sign the bid documents; and 3) Authorize advertisement for construction bids (Bid Number: 2025-0109). FUNDING: Accumulative Capital Outlay Fund.
Attachments: 1. A - Blue Route Approval, 2. B - 2025-0109 JOC Bid
Related files: 23-1449, 13-0915
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Facilities, a division of the Chief Administrative Office, recommending the Board consider the following pertaining to the annual Job Order Contracting Bid that allows the County to efficiently bid multiple construction jobs throughout the year based on competitively bid unit prices:

1) Approve and adopt the bid, specifications, and contract documents;

2) Approve and authorize the Chair to sign the bid documents; and

3) Authorize advertisement for construction bids (Bid Number: 2025-0109).

 

FUNDING:  Accumulative Capital Outlay Fund.

Body

DISCUSSION / BACKGROUND

Job Order Contracting (JOC) is a procurement process that helps government entities complete a large number of repairs, maintenance, and renovation projects with a single competitively bid contract. Unlike traditional bidding, where each project is identified, designed, and put out to bid, Job Order Contracting establishes competitively bid prices up front and eliminates the need to separately bid each project.

 

Contractors will competitively bid unit prices. The contract is then awarded to the bidder chosen as the lowest responsive qualified bidder. Multiple contracts are awarded to allow the department the flexibility to utilize multiple vendors during peak demands. Once the contract is in place, the Facilities Division may have the contractor perform a series of individual projects as separate job orders and the prices are never negotiated. The contractor is paid the pre-set unit prices multiplied by the competitively bid adjustment factor. This greatly reduces change orders and disputes.

 

The Division intends to award contracts to three bidders for a compensation amount not to exceed $2,500,000 to each bidder. The Department does not anticipate utilizing all $7.5M of the contract value related to these three awards, but needs the flexibility to use up to $2.5M annually with any one contractor or with multiple contractors depending on the timing and availability of funds.  At no time will the Department exceed their annual budgeted appropriations approved by the Board of Supervisors.

 

Upon approval by the Board, Procurement and Contracts will set the bid schedule, advertise for bids, and return to the Board with a recommendation for award at the conclusion of the bid process. The Construction Task Catalog and Technical Specification documents are not attached to this Board item due to the size. Both are available for viewing in PDF format at the Clerk of the Board’s Office and Procurement and Contracts Division Office.

 

ALTERNATIVES

The Board could decline the bids and the Division would not have a Job Order Contract program.

 

PRIOR BOARD ACTION

Legistar file 23-1449 - October 24, 2023 - The Board approved five-year Agreement 7966 with the Gordian Group who provides services and software to implement a Job Order Contracting program.

 

Legistar file 13-0915 - April 22, 2014 - The Board approved Resolution 039-2014 delegating authority to the Facilities Manager (up to $125,000) and Chief Administrative Officer (greater than $125,000) to execute all documentation required to implement individual task orders under the Job Order Contracting program agreements.

 

OTHER DEPARTMENT / AGENCY INVOLVEMENT

County Counsel

Procurement & Contracts

 

CAO RECOMMENDATION / COMMENTS

Approve as recommended.

 

FINANCIAL IMPACT

Funding is included in the Fiscal Year 2024-2025 Facilities Maintenance and Accumulated Capital Outlay (ACO) budgets and will be included in future years. These contracts are on an as-needed basis and the dollar amount utilized will vary each year based on need.  

 

CLERK OF THE BOARD FOLLOW UP ACTIONS

Obtain the Chair’s signature on the bid documents and forward to the Procurement and Contracts Division of the Chief Administrative Office for processing.

 

STRATEGIC PLAN COMPONENT

N/A

 

CONTACT

Chuck Harrell, Facilities Division Manager