File #: 18-0616    Version: 1
Type: Agenda Item Status: Approved
File created: In control: Board of Supervisors
On agenda: 6/26/2018 Final action: 6/26/2018
Title: Community Development Services, Long Range Planning and Department of Transportation recommending the Board: 1) Adopt the 2018 Capital Improvement Program Book as presented in Attachment B; and 2) Authorize the addition of five new projects to the 2018 CIP: a) Bass Lake Road Widening - US 50 to Serrano Parkway (CIP 72BASS); b) Latrobe Road Widening - Investment Boulevard to Golden Foothill Parkway (South)/Clubview Drive (CIP 72LATROBE); c) US 50 Westbound Auxiliary Lane - Cameron Park Drive to Cambridge Road (CIP 53US50); d) Enterprise Drive/Missouri Flat Road-Signalization (CIP 73365); and e) Industrial Drive/Missouri Flat Road-Signalization (CIP 73366). (Est. Time 15 Min.) FUNDING: Various Federal, State, and Local funding sources.
Attachments: 1. A - Staff Report, 2. B - 2018 CIP Book as amended 6-26-18, 3. C - CIP Findings of Consistency, 4. D - CORP Infrastructure Investments, 5. E - Completed projects
Related files: 18-0713, 18-0269, 19-1820, 19-1158, 19-0890, 18-1692, 18-1702, 19-1516, 19-1368

Title

Community Development Services, Long Range Planning and Department of Transportation recommending the Board:

1) Adopt the 2018 Capital Improvement Program Book as presented in Attachment B; and

2) Authorize the addition of five new projects to the 2018 CIP:

a) Bass Lake Road Widening - US 50 to Serrano Parkway (CIP 72BASS);

b) Latrobe Road Widening - Investment Boulevard to Golden Foothill Parkway (South)/Clubview Drive (CIP 72LATROBE);

c) US 50 Westbound Auxiliary Lane - Cameron Park Drive to Cambridge Road (CIP 53US50);

d) Enterprise Drive/Missouri Flat Road-Signalization (CIP 73365); and

e) Industrial Drive/Missouri Flat Road-Signalization (CIP 73366).  (Est. Time 15 Min.)

 

FUNDING:  Various Federal, State, and Local funding sources.

Body

DEPARTMENT RECOMMENDATION

Community Development Services (CDS), Long Range Planning and Department of Transportation (Transportation) recommending the Board:

1)  Adopt the 2018 Capital Improvement Program (CIP) Book as presented in Attachment B.

2)  Authorize the addition of five new projects to the 2018 CIP:

                     Bass Lake Road Widening - US 50 to Serrano Parkway (CIP #72BASS);

                     Latrobe Road Widening - Investment Boulevard to Golden Foothill Parkway (South)/Clubview Drive (CIP #72LATROBE);

                     US 50 Westbound Auxiliary Lane - Cameron Park Drive to Cambridge Road (CIP #53US50);

                     Enterprise Drive/Missouri Flat Road-Signalization (CIP #73365); and

                     Industrial Drive/Missouri Flat Road-Signalization (CIP #73366).

 

BACKGROUND/DISCUSSION

The CIP is the long-range plan for all individual capital improvement projects, including cost estimates, schedules, and funding sources.  It provides strategic direction for capital projects over a current year, 5-, 10-, and 20-year horizon.  The CIP is used as a planning tool and is updated annually as new information becomes available regarding Board priorities, funding sources, project cost estimates, and timing.

In order to ensure that growth consistent with the General Plan does not exceed available roadway capacity, the County is required to implement General Plan Policy TC-Xb and Implementation Measures TC-A and TC-B.  General Plan Policy TC-Xb and Implementation Measure TC-A require the County to prepare an annual CIP for the West Slope Road/Bridge Program specifying expenditures for roadway improvements within the next 10 years.

General Plan Policy TC-Xb and Implementation Measure TC-A also require a Major CIP and Traffic Impact Mitigation (TIM) Fee Program update every five years, in line with the major review of the General Plan, specifying expenditures for roadway improvements within the next 20 years. 

On May 10, 2018, the Planning Commission approved the Finding of Consistency of the 2018 Annual CIP with the General Plan (Attachment C).

 

The proposed 2018 CIP Book includes the following five programs:

                     West Slope Road/Bridge CIP

                     Tahoe Environmental Improvement Program (EIP)

                     Airport CIP

                     Transportation Facilities Improvement Program (TFIP)

                     Capital Overlay and Rehabilitation Program (CORP)

 

Attachment A describes each Program proposed for inclusion in the 2018 CIP Book.  A list of projects completed between 2001 and 2018 is included in Attachment E. 

 

ALTERNATIVES

The Board could choose to not adopt the 2018 CIP, which would result in Transportation not having a 2018 work plan.  The Board could choose to make changes in the 2018 CIP, which would result in a delay for the adoption and implementation of the Transportation 2018 work plan

 

OTHER DEPARTMENT/AGENCY INVOLVEMENT

N/A

 

CAO RECOMMENDATION

It is recommended that the Board approve this item.

 

FINANCIAL IMPACT

Funding for projects in the 2018 CIP comes from various Federal, State, and Local funding sources, as detailed by project in the CIP.

 

CLERK OF THE BOARD FOLLOW UP ACTIONS

N/A

 

STRATEGIC PLAN COMPONENT

The CIP is a vital part of the Infrastructure component of the County Strategic Plan.  Adequate infrastructure is necessary for the Economic Development component and a requirement of the County General Plan, and safe roads are a crucial factor in the Public Safety component of the County Strategic Plan.

 

CONTACT

Rafael Martinez, Director, Department of Transportation