File #: 24-0368    Version: 1
Type: Agenda Item Status: Approved
File created: 2/15/2024 In control: Board of Supervisors
On agenda: 2/27/2024 Final action: 2/27/2024
Title: Planning and Building Department, Planning Division, submitting for approval of the Final Map (TM-F23-0005) for the Silver Springs Unit 3 Subdivision (TM97-1330), creating a total of 47 residential lots and 3 lettered lots, on property identified as Assessor’s Parcel Number 115-370-003 located on the east side of Silver Springs Parkway approximately 1,400 feet south of the intersection with Green Valley Road in the Bass Lake area (Attachment E, Exhibits A & B), and recommending the Board: 1) Approve the Final Map (TM-F23-0005) for Silver Springs Unit 3 (Attachment E, Exhibit C); 2) Approve and authorize the Chair to sign the Agreement to Make Subdivision Improvements (Attachment B); and 3) Approve and authorize the Chair to sign the Offsite Road Improvement Agreement for the Offsite Pioneer Place Lift Station Force Main Extension located along Bass Lake Road from Barbary Way to Madera Way (Attachment C). (Supervisorial District II) FUNDING: Developer-Funded.
Attachments: 1. A - Counsel Approval - Subdivision Improvement Agreement, 2. B - Counsel Approval - Road Improvement Agreement, 3. C - Subdivision Improvement Agreement, 4. D - Road Improvement Agreement, 5. E - Subdivision Improvement Agreement Bonds, 6. F - Road Improvement Agreement Bonds, 7. G - Combined Exhibits, 8. H - Verification of Conformance to Conditions of Approval, 9. Public Comment BOS Rcvd. 2-27-2024, 10. Executed Road Improvement Agreement, 11. Executed Subdivision Improvement Agreement
Related files: 06-1539
Title
Planning and Building Department, Planning Division, submitting for approval of the Final Map (TM-F23-0005) for the Silver Springs Unit 3 Subdivision (TM97-1330), creating a total of 47 residential lots and 3 lettered lots, on property identified as Assessor’s Parcel Number 115-370-003 located on the east side of Silver Springs Parkway approximately 1,400 feet south of the intersection with Green Valley Road in the Bass Lake area (Attachment E, Exhibits A & B), and recommending the Board:
1) Approve the Final Map (TM-F23-0005) for Silver Springs Unit 3 (Attachment E, Exhibit C);
2) Approve and authorize the Chair to sign the Agreement to Make Subdivision Improvements (Attachment B); and
3) Approve and authorize the Chair to sign the Offsite Road Improvement Agreement for the Offsite Pioneer Place Lift Station Force Main Extension located along Bass Lake Road from Barbary Way to Madera Way (Attachment C). (Supervisorial District II)

FUNDING: Developer-Funded.
Body
DISCUSSION / BACKGROUND
The Silver Spring Unit 3 Final Map (TM-F23-0005) would create a total of 47 residential lots and 3 lettered lots (Attachment E, Exhibit C). The Silver Springs Unit 3 Final Map is based on the Silver Springs Tentative Subdivision Map (TM97-1330) originally approved by the Board of Supervisors on December 15, 1998 (Agenda Item No. 82), subsequently modified by the Planning Director through approval of a substantial conformance on May 24, 2009 (Attachment E, Exhibit D), and the Silver Springs Phasing Plan (Attachment E, Exhibit E).

The original expiration of TM97-1330 (Silver Springs) was December 15, 2001. However, the project has benefited from numerous legislative extensions, has exhausted all six one-year discretionary extensions, and Silver Springs Phase 1 was approved by the Board of Supervisors on September 26, 2006 (File No. 06-1539, Item No. 15) extending the map for 36 months, resulting in an expiration date of March 2, 2024. Approval of the Silver Springs ...

Click here for full text