File #: 21-1434    Version: 1
Type: Agenda Item Status: Approved
File created: 8/25/2021 In control: Board of Supervisors
On agenda: 9/28/2021 Final action: 9/28/2021
Title: Department of Transportation recommending the Board approve and authorize the Chair to sign the Green Valley Road Road Improvement Agreement 21-54989, between the County and the Developer, Summerbrook, El Dorado, LLC. FUNDING: Developer Funded.
Attachments: 1. A - Approved CRS, 2. B - Agmt 21-54989, 3. C - Performance and L&M Bonds, 4. D - Project Improvement Plans, 5. Executed Agreement 21-54989
Related files: 23-1467, 24-0900
Title
Department of Transportation recommending the Board approve and authorize the Chair to sign the Green Valley Road Road Improvement Agreement 21-54989, between the County and the Developer, Summerbrook, El Dorado, LLC.

FUNDING: Developer Funded.
Body
DISCUSSION / BACKGROUND
The Tentative Map (TM 07-1440-R-2) for the Summer Brook project was approved by the Planning Commission on August 9, 2018. Department of Transportation (Transportation) is recommending the Board approve and authorize the Chair to sign the Green Valley Road Road Improvement Agreement 21-54989 (Agreement), between the County and the Developer, Summerbrook, El Dorado, LLC (Developer).

In accordance with the Conditions of Approval, the Developers shall improve the frontages along the north side of Green Valley Road by rebuilding the existing road surfaces, widening Green Valley Road, adding traffic signs, installing water lines, sewer lines, and headwalls, modifying the existing storm drain culverts, and restriping the roadways. The new intersection of Green Valley Road and the internal Silverleaf Drive shall include the construction of a raised traffic island, effecting a Right-In, Right-Out only configuration. The Developer shall also modify the existing signal at the Pleasant Grove Middle School intersection on Green Valley Road, to allow for connection of the new internal Summer Brook Drive.

The work described in the Agreement is anticipated to start in Fall 2021, and onsite improvements are currently underway. No full closures of any roadways are currently anticipated; however, construction related delays to traffic may occur.

Approval of this Agreement will allow the Developers to make improvements to Green Valley Road, as necessary to complete the project.

ALTERNATIVES
This Agreement is necessary for the Developers to construct the Green Valley Road Offsite Improvements. If the Agreement is not approved, the Developers would not be able to construct the necessary improve...

Click here for full text