File #: 15-0991    Version:
Type: Agenda Item Status: Approved
File created: 8/14/2015 In control: Board of Supervisors
On agenda: 9/1/2015 Final action: 9/1/2015
Title: Community Development Agency, Development Services Division, submitting for approval Final Map (TM04-1391-F-4) for Carson Creek Unit 1, Phase B creating a total of 47 residential lots, ranging in size from 6,620 to 14,850 square feet, and 6 lettered lots on property identified by Assessor’s Parcel Numbers 117-570-01 and 117-570-05 located on the south side of Golden Foothill Parkway 0.41 mile west of the intersection with Latrobe Road in the El Dorado Hills Area and recommending the Board consider approving the Final Map for Carson Creek Unit 1, Phase B Subdivision (Supervisorial District 1). (Cont. 8/25/15, Item 15) FUNDING: N/A (Developer funded subdivision improvements).
Attachments: 1. 2A - AGMT 15-54291 ZOB Formation Agmt-1 9-1-15, 2. 2B - Blue Route for Zone of Benefit 9-1-15, 3. Executed Zone of Benefit 98310 (9-1-15), 4. A - Exhibits A-K 8-25-15, 5. B - Board Hearing Letter 8-25-15

Title

Community Development Agency, Development Services Division, submitting for approval Final Map (TM04-1391-F-4) for Carson Creek Unit 1, Phase B creating a total of 47 residential lots, ranging in size from 6,620 to 14,850 square feet, and 6 lettered lots on property identified by Assessor’s Parcel Numbers 117-570-01 and 117-570-05 located on the south side of Golden Foothill Parkway 0.41 mile west of the intersection with Latrobe Road in the El Dorado Hills Area and recommending the Board consider approving the Final Map for Carson Creek Unit 1, Phase B Subdivision (Supervisorial District 1). (Cont. 8/25/15, Item 15)

 

FUNDING:  N/A (Developer funded subdivision improvements).

Body

DEPARTMENT RECOMMENDATION

Community Development Agency, Development Services Division recommending the Board approve the Final Map (TM04-1391-F4) for Carson Creek Unit 1, Phase B.

 

DISCUSSION / BACKGROUND

The subject parcels are located within the master planned development of the Carson Creek Specific Plan (Exhibits A and B). In February 2008, the Carson Creek Tentative Map was approved creating a total of 302 age-restricted residential lots and 24 large lots for phasing purposes (Exhibit C). In January 2014, a revised tentative map with a reduced count of 285 age-restricted and 18 large lots was found substantially in conformance with the approved tentative map and was administratively approved by the Development Services Director. On August 5, 2014, a large lot final map was approved creating a total of 18 large lots for phasing purposes, including 11 lots associated with future development, five open space lots, and two landscape lots (Exhibit D).  On August 6, 2014, a second revision to the tentative map was found to be substantially in conformance with the first revision to the tentative map and was administratively approved by the Development Services Director (Exhibit E). This final map would create a total of 47 age-restricted residential lots, ranging in size from 6,620 to 14,850 square feet, and 6 lettered lots for private roads, landscaping, and open space (Exhibit F).

 

The Final Map conforms to the approved 2nd Revised Tentative Map approved by the Development Services Director on August 6, 2014 (Exhibit E).  Approval of this final map would also establish the zoning for the Carson Creek Unit 1, Phase B Subdivision (Exhibit H).  Exhibit I details the verification of the Final Map for conformance with the approved conditions of approval for the Tentative Map. County departments and affected outside agencies, including El Dorado Hills Fire Department, Transportation Division, and County Surveyor's Office, have recommended approval of the map. A meter award letter from El Dorado Irrigation District has been secured for public water, recycled water, and sewer services for the subdivision (Exhibit J). The Subdivision Improvement Agreement has been approved by Transportation Division for Carson Creek Unit 1, Phase A through D Subdivisions (Exhibit K), subject to authorization by the Board Chair. 

 

Environmental Review:  The review of the Final Map is a ministerial process and is Statutorily Exempt from environmental review under Section 15268(b)(3) of the CEQA Guidelines.

 

EXHIBITS

 

Exhibit A - Assessor’s Parcel Map

Exhibit B - Location Map

Exhibit C - Original Approved Carson Creek Tentative Map (TM04-1391)

Exhibit D - Approved Large Lot Final Map (TM04-1391-F2)

Exhibit E - 2nd Revised Approved West Valley Village Lot X Tentative Map (TM04-1391-R2)

Exhibit F - Final Map for Carson Creek Unit 1, Phase B (TM04-1391-F4)

Exhibit G - Carson Creek Specific Plan-Land Use Plan

Exhibit H - Carson Creek Specific Plan Proposed Zoning Map

Exhibit I - Verification of Final Map Conformance with Conditions of Approval

Exhibit J - EID Meter Award Letter

Exhibit K - Carson Creek Unit 1 Phasing Exhibit

 

ALTERNATIVES

N/A - Developer-funded subdivision improvements

 

OTHER DEPARTMENT / AGENCY INVOLVEMENT

El Dorado Hills Fire Department, Surveyor's Office, and the Community Development Agency, Transportation Division.

 

CAO RECOMMENDATION

CAO recommending the Board move staff's recommendations.

 

FINANCIAL IMPACT

N/A

 

CLERK OF THE BOARD FOLLOW UP ACTIONS

Clerk to send copy of correspondence to the Development Services Division.

 

CONTACT

Roger Trout, Development Services Division Director

Community Development Agency