File #: 08-0539    Version:
Type: Agenda Item Status: Approved
File created: 4/9/2008 In control: Board of Supervisors
On agenda: 6/3/2008 Final action: 6/3/2008
Title: Transportation Department recommending award of Construction Contract for the Apalachee Phase 3B Erosion Control Project, Contract No. 95183 to the lowest responsive, responsible bidder; and Chairman be authorized to sign the Contract subject to review and approval of the final contract documents by County Counsel and Risk Management. FUNDING: U.S. Forest Service, U. S. Bureau of Reclamation, California Tahoe Conservancy
Attachments: 1. 6-3-08 BOS Award Letter, 2. Letter from R. Shepard att'd 6-2-08 (6-3-08).pdf, 3. Letter from R. Shepard att'd 6-9-08.pdf
Title
Transportation Department recommending award of Construction Contract for the Apalachee Phase 3B Erosion Control Project, Contract No. 95183 to the lowest responsive, responsible bidder; and Chairman be authorized to sign the Contract subject to review and approval of the final contract documents by County Counsel and Risk Management.

FUNDING: U.S. Forest Service, U. S. Bureau of Reclamation, California Tahoe Conservancy

Body
BUDGET SUMMARY:
Total Estimated Cost $

Funding
Budgeted $
New Funding $
Savings $
Other $
Total Funding Available $
Change To Net County Cost $

Fiscal Impact/Change to Net County Cost: The Engineer's cost estimate for this project is approximately $2.1 million. There is no Net County Cost associated with this item.


Background:
On April 29, 2008, your Board approved the Apalachee 3B Erosion Control Project’s (Project) Plans and Specifications and authorized the Department to advertise for construction bids, with the bid opening scheduled for May 23,2008.

Reason for Recommendation:
The Department opened bids on Friday, May 23, 2008. Upon the conclusion of the five day protest period, the Department will inform the Board via hardcopy letter to identify the lowest responsive bidder for the Project.

The Phase 3B Project area is located in eastern El Dorado County, in the Tahoe Basin, east of U.S. Highway 50 and west of Pioneer Trail. The Phase 3B Project area is generally bounded by Pioneer Trail to the southeast, Trout Creek to the east, and the Upper Truckee River and the rescinded Caltrans highway corridor to the west. The Phase 3B Project area includes Tahoe Paradise Additions Nos. 2, 4, and 5.

Due to the large size and cost of constructing the Phase 3B Project, the area has been subdivided into two bid schedules (Schedule A and Schedule B). The Phase 3B Project will be bid as a Base Bid (Schedule A) and Additive Alternative Bid (Schedule B) unde...