File #: 21-0833    Version: 1
Type: Agenda Item Status: Approved
File created: 5/8/2021 In control: Board of Supervisors
On agenda: 6/8/2021 Final action: 6/8/2021
Title: Department of Transportation recommending the Board: 1) Approve and authorize the Chair to sign the Notice of Acceptance with Drill Tech Drilling & Shoring, Inc. for the Green Valley Road Slipout Repair Project, Contract 2776, Capital Improvement Program project number 78707/36102008; and 2) Approve and authorize the Clerk of the Board to release the Payment and Performance Bonds to the Surety upon notification from the Department of Transportation, after the one-year guarantee period. FUNDING: Federal Highway Administration anticipated reimbursement (88.53%), California Disaster Assistance Act anticipated reimbursement (8.6%), Road Fund & Regional Surface Transportation Program Exchange Funds - Caltrans (2.87%). (Local, State, and Federal Funds)
Attachments: 1. A - Notice of Acceptance, 2. Executed NOA
Related files: 20-1507, 19-1420, 18-1250, 18-1967
Title
Department of Transportation recommending the Board:
1) Approve and authorize the Chair to sign the Notice of Acceptance with Drill Tech Drilling & Shoring, Inc. for the Green Valley Road Slipout Repair Project, Contract 2776, Capital Improvement Program project number 78707/36102008; and
2) Approve and authorize the Clerk of the Board to release the Payment and Performance Bonds to the Surety upon notification from the Department of Transportation, after the one-year guarantee period.

FUNDING: Federal Highway Administration anticipated reimbursement (88.53%), California Disaster Assistance Act anticipated reimbursement (8.6%), Road Fund & Regional Surface Transportation Program Exchange Funds - Caltrans (2.87%). (Local, State, and Federal Funds)
Body
DISCUSSION / BACKGROUND
The contract for the Project was approved by the Board on January 29, 2019 (Legistar 18-1967, Item 21). All items were completed by October 14, 2020. Recordation of the Notice of Acceptance (NOA) will start legal time frames for guarantees, a lien period, and return of retention monies. Recordation of the NOA will also start the one-year time frame for releasing the Payment and Performance Bonds to the Surety.

Direct Construction Cost Summary:

Original Bid Price $ 947,677.00
Contract Item Cost $ 926,756.00
Contract Change Order Cost $ 235,783.81
Total Direct Construction Cost $ 1,162,539.81

Major Contract Change Orders (CCO) on the Project dealt with the following:
· Contractor remobilization for broadband utility relocation delay;
· Additional guardrail installation;
· Additional Rock Slope Protection; and
· Delineator installation along Green Valley Road.

Contract Change Order 5 was brought to the Board for approval on December 12, 2020 (Legistar 20-1507, Item 25) which included remobilization, guardrail installation, additional rock slope protection, existing pipe abandonment, and tree removal.

The final costs listed have been agreed to by the Contractor and appr...

Click here for full text