File #: 08-1404    Version:
Type: Agenda Item Status: Approved
File created: 5/26/2009 In control: Board of Supervisors
On agenda: 12/15/2009 Final action: 12/15/2009
Title: Transportation Department recommending the following pertaining to the Rite Aid at Cameron Ranch Project: 1) Accept as complete the constructed improvements at the intersection of Green Valley Road and Starbuck Road; 2) Reduce Performance Bond No. 4363217 by $550,091.92 to $61,121.32 to guarantee against defective work, labor done or defective materials furnished and release after one year if no claims are made; and 3) Hold Laborers and Materialmens Bond No. 4363217 in the amount of $611,213.24 to guarantee payment to persons furnishing labor, materials or equipment and release in six months if no claims are made. FUNDING: Developer, Celtic Properties
Attachments: 1. Contract Route Sheet.pdf, 2. RIA #AGMT 07-1523.pdf, 3. Conditions of Approval.pdf, 4. RIA L&M Bond & Bond Rider.pdf, 5. RIA Perf Bond & Bond Rider.pdf, 6. Improvmmt Plans Cover Sheet-Site Location.pdf, 7. 3A - Vicinity Map Rite Aid.pdf
Title
Transportation Department recommending the following pertaining to the Rite Aid at Cameron Ranch Project:
1) Accept as complete the constructed improvements at the intersection of Green Valley Road and Starbuck Road;
2) Reduce Performance Bond No. 4363217 by $550,091.92 to $61,121.32 to guarantee against defective work, labor done or defective materials furnished and release after one year if no claims are made; and
3) Hold Laborers and Materialmens Bond No. 4363217 in the amount of $611,213.24 to guarantee payment to persons furnishing labor, materials or equipment and release in six months if no claims are made.

FUNDING: Developer, Celtic Properties
Body
Fiscal Impact/Change to Net County Cost:
Per Section 17 ACCEPTANCE of Road Improvement Agreement #AGMT 07-1523, the County (Board of Supervisors) will accept the road improvements for maintenance upon completion of all the work and fulfillment of the conditions of the Agreement. Long term there will be some financial impact to the County as future maintenance of the facilities will affect the Department's Road Fund budget. There is no cost to the County General Fund.

Background:
On September 30, 2008, the Board of Supervisors approved Road Improvement Agreement # AGMT 07-1523 between the County and Celtic Properties. Under the conditions of approval for the Rite Aid at Cameron Ranch project, the Developer was required to improve the frontages along the north side of Green Valley Road and the east side of Starbuck Road. The roadway improvements included rebuilding the existing road surfaces, constructing a raised median on Green Valley Road, adding sidewalks, relocating a traffic signal pole, installing water, sewer and storm drain lines, and restriping the roads. In the interest of public safety and in anticipation of a future capital improvement project, Condition No.15.a was modified and reduced in scope.

Reason for Recommendation:
The road improvements have been inspected and were found to be com...