File #: 23-0851    Version: 1
Type: Agenda Item Status: Approved
File created: 4/14/2023 In control: Board of Supervisors
On agenda: 6/6/2023 Final action: 6/6/2023
Title: Department of Transportation recommending the Board: 1) Authorize the Chair to sign Resolution 086-2023 and adopt the 2023 Capital Improvement Program (CIP) as presented in Attachment E; and 2) Return the project, Latrobe Road Widening - Investment Boulevard to Golden Foothill Parkway South/Clubview Drive, CIP 36105055, to the unfunded list and not add it to the 2023 CIP. FUNDING: Various Federal, State, and Local funding sources, including Traffic Impact Fee Program, Missouri Flat Area Master Circulation and Financing Plan, Road Fund, Tribe Funds, Accumulative Capital Outlay, Developer Advanced Funds, Sacramento Municipal Utility District, and/or General Fund.
Attachments: 1. A - Approved Resolution Route Sheet, 2. B - 2023 CIP Book Adoption Resolution, 3. C - Planning Commission Finding of Consistency, 4. D - 2023 Project Change Table, 5. E - Proposed 2023 CIP Book, 6. Auditor's Comment BOS Rcvd. 6-5-2023, 7. Executed Resolution 086-2023
Related files: 23-0055, 23-0611, 23-1136, 23-1336, 24-0016, 24-0017, 24-0634, 24-1875, 23-1310, 23-1902, 23-2060, 23-2071, 24-0239, 24-0327
Title
Department of Transportation recommending the Board:
1) Authorize the Chair to sign Resolution 086-2023 and adopt the 2023 Capital Improvement Program (CIP) as presented in Attachment E; and
2) Return the project, Latrobe Road Widening - Investment Boulevard to Golden Foothill Parkway South/Clubview Drive, CIP 36105055, to the unfunded list and not add it to the 2023 CIP.

FUNDING: Various Federal, State, and Local funding sources, including Traffic Impact Fee Program, Missouri Flat Area Master Circulation and Financing Plan, Road Fund, Tribe Funds, Accumulative Capital Outlay, Developer Advanced Funds, Sacramento Municipal Utility District, and/or General Fund.
Body
DISCUSSION / BACKGROUND
The Capital Improvement Program (CIP) is the long-range plan for all individual transportation capital improvement projects, including cost estimates, schedules, and funding sources. It provides strategic direction for capital projects over a current year, 5-, 10-, and 20-year horizon. The CIP is used by the Department of Transportation (Transportation) as a planning tool and is updated annually as new information becomes available regarding Board priorities, funding sources, project cost estimates, and timing.

In order to ensure that traffic generated by growth consistent with the General Plan does not exceed available roadway capacity, the County is required to implement General Plan Policy TC-Xb and Implementation Measures TC-A and TC-B. General Plan Policy TC-Xb and Implementation Measure TC-A requires the County to prepare an annual CIP for the West Slope Road/Bridge Program specifying expenditures for roadway improvements within the next 10 years.

General Plan Policy TC-Xb and Implementation Measure TC-A also require a Major CIP and Traffic Impact Mitigation (TIM) Fee Program update every five years, concurrent with the major review of the General Plan, specifying expenditures for roadway improvements within the next 20 years. The last Major Update to the Traff...