File #: 23-1336    Version: 1
Type: Agenda Item Status: Approved
File created: 7/3/2023 In control: Board of Supervisors
On agenda: 8/22/2023 Final action: 8/22/2023
Title: Department of Transportation recommending the Board consider the following: 1) Approve and authorize the Chair to sign the Notice of Acceptance with North Star Construction & Engineering, Inc. for the Oflyng Water Quality Project, Capital Improvement Project number 36107016, Contract 3962; and 2) Approve and authorize the Clerk of the Board to release the Payment and Performance Bonds to the Surety upon notification from the Department of Transportation after the one-year guarantee period. (Supervisorial District V) FUNDING: United States Forest Service (82% - Federal), State Water Resource Control Board (4% - State), and Tahoe Regional Planning Agency - Water Quality Mitigation (14% - Local).
Attachments: 1. A - Notice of Acceptance, 2. Executed Notice of Acceptance
Related files: 23-0851, 22-1147, 22-0227
Title
Department of Transportation recommending the Board consider the following:
1) Approve and authorize the Chair to sign the Notice of Acceptance with North Star Construction & Engineering, Inc. for the Oflyng Water Quality Project, Capital Improvement Project number 36107016, Contract 3962; and
2) Approve and authorize the Clerk of the Board to release the Payment and Performance Bonds to the Surety upon notification from the Department of Transportation after the one-year guarantee period. (Supervisorial District V)

FUNDING: United States Forest Service (82% - Federal), State Water Resource Control Board (4% - State), and Tahoe Regional Planning Agency - Water Quality Mitigation (14% - Local).
Body
DISCUSSION / BACKGROUND
The contract for the Oflyng Water Quality Project (Project) was approved by the Board on July 26, 2022 (Legistar# 22-1147, Item 24). Construction started on August 29, 2022, and was completed on June 23, 2023. Recordation of the Notice of Acceptance (NOA) will start legal time frames for guarantees, a lien period, and the return of retention monies. Recordation of the NOA will also begin the one-year time frame for releasing the Payment and Performance Bonds to the Surety.

Direct Construction Cost Summary:

Original Bid Price $1,219,658.20
Contract Item Cost $1,145,285.00
Contract Change Order Cost $70,395.00
Total Direct Construction Cost $1,215,680.00
Direct Construction Budget $1,341,624.02

Major Contract Change Orders (CCO) on the Project dealt with the following:
· Additional tree removal;
· Construction of modified drainage inlets; and,
· Mill and replacement of existing asphalt pavement.

The final costs listed are estimates. Transportation will be closing out the Project with the Contractor and finalizing costs over the coming weeks. Any significant deviations from the estimates above that exceed Transportation’s allocated authority will be brought back to the Board for review and approval in a subsequent agen...

Click here for full text