File #: 11-0598    Version: 1
Type: Agenda Item Status: Approved
File created: 5/25/2011 In control: Board of Supervisors
On agenda: 8/16/2011 Final action: 8/16/2011
Title: Department of Transportation recommending the Board authorize the Department to proceed with ordering and payment of title reports and certified appraisals to commence the acquisition process for the Diamond Springs Parkway - Phase 1 Project, CIP No. 72334, affecting portions of the following subject parcels: APN 051-250-04, Diana Lynn Hembree; APN 051-250-06, Merrill J. DeBenning; APN 051-250-07, Masonic Homes of California; APN 051-250-08, Thomas Jefferson and Kathryn S. DeBenning; APN 054-341-04, Cheryl L. Tyler; APN 054-342-15, Gloria L. Winstead, Randy Green and Ginger Lich; APN 054-342-20, Charles T. and Sheila A. Sweet; APN 054-342-23, Randy Green, Ginger Lich and Gloria L. Winstead; APN 054-342-36, Randy Green, Ginger Lich, and Gloria L. Winstead; APN 054-351-19, Terry W. and Ellen Ambroff; APN 051-461-37, Piedmont Oak Estates, LLC.; and APN 051-461-54, Piedmont Oak Estates, LLC. FUNDING: 2004 General Plan Traffic Impact Mitigation Fees.
Attachments: 1. A - Vicinity Map
Title
Department of Transportation recommending the Board authorize the Department to proceed with ordering and payment of title reports and certified appraisals to commence the acquisition process for the Diamond Springs Parkway - Phase 1 Project, CIP No. 72334, affecting portions of the following subject parcels: APN 051-250-04, Diana Lynn Hembree; APN 051-250-06, Merrill J. DeBenning; APN 051-250-07, Masonic Homes of California; APN 051-250-08, Thomas Jefferson and Kathryn S. DeBenning; APN 054-341-04, Cheryl L. Tyler; APN 054-342-15, Gloria L. Winstead, Randy Green and Ginger Lich; APN 054-342-20, Charles T. and Sheila A. Sweet; APN 054-342-23, Randy Green, Ginger Lich and Gloria L. Winstead; APN 054-342-36, Randy Green, Ginger Lich, and Gloria L. Winstead; APN 054-351-19, Terry W. and Ellen Ambroff; APN 051-461-37, Piedmont Oak Estates, LLC.; and APN 051-461-54, Piedmont Oak Estates, LLC.

FUNDING: 2004 General Plan Traffic Impact Mitigation Fees.
Body
BUDGET SUMMARY:
Total Estimated Cost $6,600

Funding
Budgeted $6,600
New Funding $
Savings $
Other $
Total Funding Available $6,600
Change To Net County Cost $0

Fiscal Impact/Change to Net County Cost:
Funding for this portion of the acquisition process will be provided by 2004 General Plan Traffic Impact Mitigation (TIM) Fees.

Background:
The Diamond Springs Parkway - Phase 1 Project (Project), originally known as the Missouri Flat Pleasant Valley Connector, was initiated to improve traffic circulation and safety through and around the historic town of Diamond Springs and has been in various stages of planning and design for the past fifteen years.

The Project is located south of the Missouri Flat Road/US 50 Interchange, east of Missouri Flat Road, north of the community of Diamond Springs, and west of SR-49, and is also inclusive of improvements to SR-49/Diamond Road, from Finch Road to the intersection of SR-49/Pleasant Vall...

Click here for full text