File #: 19-0404    Version: 1
Type: Agenda Item Status: Approved
File created: 3/7/2019 In control: Board of Supervisors
On agenda: 3/19/2019 Final action: 3/19/2019
Title: HEARING - Chief Administrative Office, Facilities Division, recommending the Board: 1) Conduct a public hearing to adopt and authorize the Chair to sign the Solar Power Purchase Agreement RES-BCT and the Solar Power Purchase Agreement NEM (PPA) and related Cost Reimbursement Agreement (CRA) concerning the County’s Solar Project; 2) Adopt and authorize the Chair to sign Resolution 031-2019 making the required findings pursuant to Government Code 4217; and 3) Authorize the Chief Administrative Officer, or designee, to execute further documents relating to the PPA/CRA agreements, including Change Orders which do not impact the overall monetary value more than 10%. (Est. Time: 10 Min.) FUNDING: Components of the PPA and CRA provide cost reimbursement to the County over a 25 year period.
Attachments: 1. A - 4217 Board Resolution, 2. B - PPA -NEM, 3. C - PPA -RESBCT, 4. D - Cost Reimbursement Agreement, 5. E - EDC BOS Meeting Presentation 3.19.19, 6. F - Resolution Blue Route Approval, 7. G - PPA & CRA Blue Route Approval, 8. H - Pro Forma #2 Feasibility Study, 9. Public Comment Rcvd 3-19-19 BOS 3-19-19, 10. Executed Solar Power Purchase Agreement for the NEM Solar Facility, 11. Executed Solar Power Purchase Agreement RES-BCT Solar Facilty, 12. Executed Resolution 031-2019, 13. Executed Cost Reimbursement Agreement Between County and Provider
Related files: 18-1228, 18-1645, 19-0239, 19-0640, 20-0499, 19-0325, 19-1806, 20-1224
Title
HEARING - Chief Administrative Office, Facilities Division, recommending the Board:
1) Conduct a public hearing to adopt and authorize the Chair to sign the Solar Power Purchase Agreement RES-BCT and the Solar Power Purchase Agreement NEM (PPA) and related Cost Reimbursement Agreement (CRA) concerning the County’s Solar Project;
2) Adopt and authorize the Chair to sign Resolution 031-2019 making the required findings pursuant to Government Code 4217; and
3) Authorize the Chief Administrative Officer, or designee, to execute further documents relating to the PPA/CRA agreements, including Change Orders which do not impact the overall monetary value more than 10%. (Est. Time: 10 Min.)

FUNDING: Components of the PPA and CRA provide cost reimbursement to the County over a 25 year period.
Body
DISCUSSION / BACKGROUND
On March 5th, 2019, the Board was provided four PPA/CRA options regarding the County’s Solar Project. The Board directed staff to implement Option C which preserves the northerly buildable approximate 2 ½ acres for a County building not presently identified and construct a smaller solar farm on the southerly portion including additional carport arrays on the Public Safety Facility southern parking lot.

RES-BCT Option C - 25-year economic benefit approximately $1,850,000 (as a result of final engineering to accommodate Public Safety Facility operational requirements, the projected economic benefit has decreased slightly to $1,626,000 from the March 5th, 2019 presentation to the Board).

Public Safety Facility NEM - - 25-year economic benefit approximately $1,669,000 (as a result of final engineering to accommodate Public Safety Facility operational requirements, the projected economic benefit has decreased slightly to $1,600,000 from the March 5th, 2019 presentation to the Board).

Highlights concerning the PPA/CRAs output guarantee, purchase option (i.e., buyout rights) and the County’s early termination rights are outlined as follows:

Pro...