Title: Department of Transportation recommending the Board consider the following pertaining to the Enterprise Drive & Industrial Drive Intersection Improvements Project, Capital Improvement Program project numbers 36105052/36105053, Contract No. 6286: 1) Approve and adopt the Plans and Contract Documents and authorize the Chair to sign the Plans; and 2) Authorize advertisement for construction bids. FUNDING: TIM - Zn 1-7 (10%), Tribe (53%), Accumulative Capital Outlay (ACO) (13%), General Fund (24%). (No Federal Funds)
Attachments: 1. A - Contract Documents.pdf, 2. B - Routing Sheet.pdf, 3. C - Project Plans.pdf, 4. Executed Final Plans
Related files: 21-0624, 18-1493, 21-0304, 23-1020, 24-0681
Title
Department of Transportation recommending the Board consider the following pertaining to the Enterprise Drive & Industrial Drive Intersection Improvements Project, Capital Improvement Program project numbers 36105052/36105053, Contract No. 6286:
1) Approve and adopt the Plans and Contract Documents and authorize the Chair to sign the Plans; and
2) Authorize advertisement for construction bids.

FUNDING: TIM - Zn 1-7 (10%), Tribe (53%), Accumulative Capital Outlay (ACO) (13%), General Fund (24%). (No Federal Funds)
Body
DISCUSSION / BACKGROUND
The Enterprise Drive and Industrial Drive Intersection Improvements Project (Project) will remove the temporary traffic signal at Missouri Flat Road and Industrial Drive and replace it with a permanent traffic signal. This Project will also signalize the intersection of Missouri Flat Road and Enterprise Drive as well as construct turn lanes and realign Industrial Drive.

This Project does not have federal funding; thus, only California Environmental Quality Act (CEQA) compliance is required. A CEQA Addendum to the EIR was approved by the Board on October 16, 2018 (#18-1493). This Project does not require any environmental permits.

All needed right of way has been secured for the project.

ALTERNATIVES
1) The Board could choose not to approve the Contract Documents. Transportation will make any changes requested by the Board and return at a later date.
2) The Board could choose not to authorize advertisement for construction bids. Transportation will make any changes requested by the Board and return at a later date.
3) The Board could choose to cancel the Project.

PRIOR BOARD ACTION
On October 16, 2018 (Item 3, Legistar #18-1493) the Board approved the addendum to the Public Safety EIR for the signalization projects.

OTHER DEPARTMENT / AGENCY INVOLVEMENT
County Counsel and Risk Management have reviewed and approved the Plans and Contract Documents.

CAO RECOMMENDATION / COMMENTS
Approve staff recommendat...