DEPARTMENT RECOMMENDATION
Community Development Agency, Transportation Division (Transportation), recommending the Board consider the following:
1) Approve and authorize the Chair to sign the Notice of Acceptance with Don Garcia Excavating & Paving, Inc. for the Black Bart Avenue, Barbara Avenue and Martin Avenue Overlay Project (Project), CIP No. 72188, Agreement PW No. 15-31100, P&C No. 386-C1599; and
2) Authorize the Clerk of the Board to release the Payment and Performance Bonds to the Surety upon notification from Transportation after the one-year guarantee period.
DISCUSSION / BACKGROUND
The contract for the Project was approved by the Board on August 11, 2015 (Item No. 21). Construction was substantially completed on October 9, 2015. Recordation of the Notice of Acceptance will start legal time frames for guarantees, a lien period and return of retention monies. Recordation of the Notice of Acceptance will also start the one-year time frame for releasing the Payment and Performance Bonds to the Surety.
Direct Construction Cost Summary:
Original Bid Price $ 614,283.72
Contract Item Cost $ 626,229.92
Contract Change Order Cost $ 17,284.88
Total Direct Construction Cost $ 643,514.80
Direct Construction Budget $ 715,911.72
Major Contract Change Orders (CCO) on the Project dealt with...