Title: Transportation Department recommending the Board adopt said Department’s proposed 2009 Capital Improvement Program (CIP) including the West Slope 10 Year Road/Bridge CIP, Trail CIP, 5 Year Capital Overlay and Rehabilitation Program (CORP), 5 Year Tahoe Environmental Improvement Program (EIP) and 5-7 Year Airport Capital Improvement Program (ACIP).
Attachments: 1. 1. Cover Page_Table of Contents_Executive Summary.pdf, 2. 2. Overview_10 Year WS Road_Bridge CIP.pdf, 3. 2A. Map_10 Year CIP Projects.pdf, 4. 2A. Map_20 Year CIP Projects.pdf, 5. 2A. Shelf Ready Projects Supporting Key Economic Dev Areas.pdf, 6. 2B. Area Drawings.pdf, 7. 2C. Index_Project Type.pdf, 8. 2C. WS 10 YEAR_by Project Type.pdf, 9. 2D. Projects Beyond Fiscal Year 2017_18.pdf, 10. 2E. 10 Year CIP Projects Sorted by Completion Year .pdf, 11. 2F. TIM Fee Program Cash Proformas.pdf, 12. 2G.1. Index_Project Title.pdf, 13. 2G.2. Index_Project Number.pdf, 14. 2G.3. Index_Supervisor District.pdf, 15. 3A. Overview_CORP.pdf, 16. 3B. CORP Individual Project Summaries.pdf, 17. 4. Overview_Tahoe EIP.pdf, 18. 4B. Tahoe Individual Project Summaries.pdf, 19. 4.C1 Summary of Future Tahoe EIP Projects.pdf, 20. 4C2. Tahoe Future Projects.pdf, 21. 5. Overview_Airport CIP.pdf, 22. 5A. Placerville Airport ACIP.pdf, 23. 5B. Georgetown Airport ACIP 2009-2014.pdf, 24. 6. CIP Projects by Supervisor District.pdf, 25. 7. Acronyms.pdf
Related files: 20-0960, 22-1256, 20-1110
Title
Transportation Department recommending the Board adopt said Department’s proposed 2009 Capital Improvement Program (CIP) including the West Slope 10 Year Road/Bridge CIP, Trail CIP, 5 Year Capital Overlay and Rehabilitation Program (CORP), 5 Year Tahoe Environmental Improvement Program (EIP) and 5-7 Year Airport Capital Improvement Program (ACIP).

Body
Fiscal Impact/Change to Net County Cost: The CIP is a programming document, not a budgeting document. As such it has no fiscal impacts until the projects are actually included in the Department's annual budget. There is no change to the Net County Cost.

Background:

On March 2, 2009, DOT presented its proposed CIP in a workshop forum with the Board of Supervisors and the public.
The Board provided DOT with the following (informal) direction:
· Proceed with “Alternative 2A: A Balanced CIP” for the 10 Year West Slope CIP,
· Address the question of where DOT’s proposed projects are versus the County’s key economic development areas, and
· Address ongoing maintenance costs for projects in the Tahoe EIP.

Since the workshop, DOT has completed the project details associated with all the proposed projects in the West Slope Road/Bridge CIP, Trail CIP, CORP, EIP, and ACIP. These are in the attached DOT CIP.

Note: Some of the information presented at the workshop has been updated because these programs directly feed DOT’s fiscal year 2009/10 budget; (for example, in the 10 year West Slope Road/Bridge CIP, the cost estimate for project #71336, the U.S.50 Missouri Flat 1B Interchange improvement, has been updated to reflect the engineer’s most current cost estimate because this project is scheduled to start construction in FY 09/10.) Therefore, the Department has updated the project revenues/costs accordingly which are reflected in the following pages.

The overall conclusions presented at the workshop remain the same.

To address the question of where DOT’s proposed projects are versus the County’s key economi...