File #: 23-1523    Version: 1
Type: Agenda Item Status: Approved
File created: 8/3/2023 In control: Board of Supervisors
On agenda: 9/12/2023 Final action: 9/12/2023
Title: Chief Administrative Office, Parks Division, recommending the Board: 1) Adopt the Initial Study/Mitigated Negative Declaration for the Forebay Park Improvement Project; and 2) Approve the Phasing Plan for improvements to Forebay Park. FUNDING: American Rescue Plan Act (90%), California Department of Parks and Recreation Prop 68 Per Capita Program (9%), General Fund (1%).
Attachments: 1. A - Final ISMND Forebay Park July2023, 2. B - Forebay Park Concept Plan, 3. C - Forebay Park Phasing Plan, 4. D - Forebay Cost Estimate, 5. E - Forebay Park Design Proposal
Related files: 21-0162, 21-1452, 21-1680, 21-1702, 22-0292, 22-1483, 22-1822, 22-1846, 23-1967
Title
Chief Administrative Office, Parks Division, recommending the Board:
1) Adopt the Initial Study/Mitigated Negative Declaration for the Forebay Park Improvement Project; and
2) Approve the Phasing Plan for improvements to Forebay Park.

FUNDING: American Rescue Plan Act (90%), California Department of Parks and Recreation Prop 68 Per Capita Program (9%), General Fund (1%).
Body
DISCUSSION / BACKGROUND
The FY 2021-22 Parks budget included $50,000 in General Fund to install a playground at Forebay Park in Pollock Pines. In addition, the California Drought, Water, Parks, Climate, Coastal Protection, and Outdoor Access for All Act of 2018 (Prop 68) Per Capita program allocated $400,000 in per capita funding to the County in 2021. On September 21, 2021, the Board allocated $300,000 of this funding for construction of a restroom at this site. The Board also allocated $3 million of ARPA funding for park renovation. This brings the total funding for park improvements to $3,350,000. On October 18, 2022, the Board received a presentation on community engagement efforts and the conceptual design for Forebay Park. The Board approved the design and directed staff to proceed with the environmental review process, and with developing a phasing plan and construction documents based on available funding and community priorities and implementing the park improvements (Legistar Item #22-1822). The Phasing Plan (Attachment C), and a Statement of Probable Costs (Attachment D) have been completed, with a total cost of $3,719,568.

Phasing and Costs

Phase 1A Underground utilities, paving infrastructure $ 819,456
Phase 1B Playground $ 757,860
Phase 2 Frisbee Golf, picnic areas, South trail $ 856,910
Phase 3 Dog Park, West trail $ 278,494
Phase 4 Basketball/Pickle Ball, East trail $ 386,920
Contingency (20%) $ 619,928
$3,719,568

The Phasing Plan includes all infrastructure improvements and park amenities from the approved design but does ...

Click here for full text